2025-10-21: Zoning Board Of Appeals

Click timestamps in the text to watch that part of the meeting recording.

Now I have good context from the adjacent ZBA meetings. Let me produce the analysis document.


Zoning Board of Appeals Meeting — October 21, 2025


Section 1: Agenda (Inferred)

  1. Pre-Meeting Technical Setup 00:09:19

    • Board members and remote participant troubleshoot audio/voicemail issue before formally beginning
  2. Continued Public Hearing: 40B Comprehensive Special Permit — Veterans Crossing (Pine Street) 00:10:40

    • Confirmation of quorum (five ZBA members including remote participant Tony)
    • Introduction of technical consultant Paul Havardy
    • Developer presentation of revised civil engineering plans (elevation, parking, drainage, sewer)
    • Developer presentation of updated landscaping, lighting, and arborist findings
    • Architectural updates: stair removal, egress door security, shadow study, updated rendering
    • Construction management and operational commitments
    • Withdrawal of permit and connection fee waiver requests
    • Public comment period: abutter questions on parking, driveway relocation, culvert, sewer study, rooftop equipment noise, and peer review status
    • Discussion and vote on authorizing peer review engagement
    • Motion to continue public hearing to November 18, 2025

Section 2: Speaking Attendees

Note: This transcript was produced by automated speaker diarization, which inconsistently reassigned speaker tags throughout the meeting. The identifications below represent best inferences; some tags were reused for multiple individuals across different segments.

ZBA Board Members:

  • Heather (last name not stated), ZBA Chair: Primarily [Speaker 3] — Opens and manages the hearing; introduces the consultant; moderates public comment. Designated as the board’s representative for peer review engagement. Greeted by name at 00:36:12.
  • ZBA Member (name not clearly stated): Primarily [Speaker 2] in later segments (~00:25:00 onward) — Asks detailed questions about landscaping, shade trees, and culvert; helps manage votes and the closing of the meeting. Likely a senior member or vice-chair.
  • Mike (last name not stated), ZBA Member: [Speaker 4] in voting segments (~00:46:00) — Makes formal motions for peer review authorization and continuance. Addressed by name at 00:46:01.
  • Tony (last name not stated), ZBA Member (Remote): [Speaker 4] at 00:10:32 — Fifth ZBA member participating via Zoom; experienced persistent audio/muting difficulties throughout the meeting.
  • ZBA Member (fifth in-person member): [Speaker 10] at 00:38:15 — Asks practical questions about the timing and readiness for civil peer review.

Consultant:

  • Paul Havardy, Technical Assistance Consultant: [Speaker 5] at 00:12:09 and [Speaker 6] at 00:41:16 — Present on a grant from the National Research Institute to provide technical assistance to the ZBA during the 40B process. Advises on peer review timing and the 180-day statutory clock.

Developer Team (Neighbourhood Housing / B’nai B’rith Housing):

  • Yara Varugood, Senior Project Manager: [Speaker 7] at 00:12:42 — Leads the developer presentation; summarizes changes made in response to town and community feedback; reports on meeting with Pine Street neighbors.
  • Jacob Lemieux, Civil Engineer (Hancock Associates): [Speaker 2] at 00:15:38, also [Speaker 1] in later civil segments — Presents updated site plans including building elevation, one-way parking circulation, turning analysis, grading, stormwater, sewer connection, landscaping, and lighting changes.
  • Christopher Curran, Architect (T.A.T.): [Speaker 5] at 00:25:45 — Presents architectural updates including stair removal, egress door security, and shadow study results; shows before-and-after rendering of the Pine Street perspective.
  • John Smolic, Zoning Attorney: Mentioned but unclear speaking role; likely [Speaker 9] at 00:36:58 asking about peer review scope.
  • Holly Grace (BVH): Mentioned as part of the team; speaking role unclear.

Public / Abutters:

  • Steve Gadman, 11 Pine Street: [Speaker 4] at 00:32:01 — Raises concerns about loss of on-street parking near the driveway and reiterates request to relocate the driveway entrance away from Pine Street; asks about the culvert crossing Pine Street.
  • Alicia McCarthy, 9 Pine Street: [Speaker 6] at 00:34:34 — Asks about sewer documentation and ongoing culvert maintenance responsibilities.
  • Mary Ellen Fletcher, Precinct 4 (Select Board Member): [Speaker 8] at 00:36:17 — Joins via Zoom to ask for clarification on the withdrawal of fee waivers.
  • Pine Street Resident (name not stated, online): [Speaker 7] at 00:42:17 — Suggests alternative driveway placement at the end of Pine Street near New Ocean Street; attended recent meeting with developer.
  • Pine Street Resident (rooftop equipment question): [Speaker 8] at 00:43:54 — Follows up on a prior meeting request for information about rooftop mechanical equipment decibel levels.

Staff Referenced (not present as speakers):

  • Christa (ZBA Administrator): Referenced as “Christy” — Handling logistics, document posting, and peer review coordination.
  • Gino Cresta (Director of Public Works): Referenced multiple times regarding culvert tree removal, sewer review, and driveway feasibility.
  • Mark Noonan (DPW): Referenced at 00:40:05 regarding sewer capacity review.

Section 3: Meeting Minutes

Pre-Meeting Technical Difficulties

00:09:19 The meeting began with several minutes of technical difficulty as a board member inadvertently left a voicemail recording running during the opening moments. The Chair quipped that “somebody’s gonna have to stop using voicemail.” The board then confirmed the remote participation of Tony, the fifth ZBA member required for the 40B hearing, who reported difficulty hearing the proceedings initially.

Opening of Continued Public Hearing: Veterans Crossing (40B)

00:10:40 Chair Heather called the continued hearing on the 40B Comprehensive Special Permit for Veterans Crossing to order. She recapped that the prior meeting on September 16 included a full overview of the proposed plan, abutter input, and a list of requests and concerns for the developer to address. She noted the developer team had made progress on many of those items and introduced Paul Havardy as the board’s technical consultant, present on a grant from the National Research Institute to provide guidance during the 40B process.

Paul Havardy 00:12:09 confirmed his role and indicated he had no specific items to raise at that point but was available for questions throughout.

Developer Presentation: Civil Engineering Updates

00:12:42 Yara Varugood, senior project manager for Neighbourhood Housing, introduced the development team — including zoning attorney John Smolic, civil engineer Jacob Lemieux (Hancock Associates), architect Christopher Curran (T.A.T.), and Holly Grace (BVH). She summarized that the team had worked through comments received from town staff via a September 8 memo as well as feedback from the ZBA and community at the September 16 meeting. A progress plan set and a detailed response memo had been prepared.

Varugood reported that Neighbourhood Housing had met the previous week with Pine Street neighbors as requested. 00:14:12 She identified three key concerns raised by the neighbors: (1) whether the driveway could be relocated off Pine Street, potentially through the adjacent dispensary lot; (2) whether the main building entrance could be shifted away from Pine Street; and (3) ongoing traffic and safety concerns around Pine Street and surrounding streets. On the first two items, Varugood stated the developer was “in the middle of analyzing” options and planned to work through them with the town and planning staff. No response was ready at this time.

00:15:38 Jacob Lemieux presented the updated civil plans. Key changes included:

  • Building elevation raised to 16 feet, providing two extra feet above the floodplain for climate resiliency and building code compliance.
  • One-way parking circulation adopted, enabling a loading area on the right side of the entrance while maintaining traffic flow. This prevents vehicles from parking on the roadway and blocking the building entrance.
  • No-parking striping proposed along the roadway to keep the curb cut clear for garbage truck access.
  • Turning analysis completed demonstrating that a large rear-load garbage truck can enter, collect, and exit the site — even with a vehicle parked in the loading dock area. Chair Heather asked 00:17:40 whether the fire department had reviewed this; Lemieux confirmed it had not yet been officially requested but would be reviewed as part of the standard review process.
  • Parking setback increased: The one-way circulation allowed parking to be pulled several feet further from abutting parcels, with a new three-foot landscaped buffer and four-foot fence between the project parcel and the adjacent marijuana dispensary lot.
  • Stair removal: A set of exterior stairs on the side of the front porch facing the public sidewalk was removed, requiring all pedestrian traffic to enter through the main on-site entrance.

Sewer and Drainage Updates

00:19:12 Lemieux detailed grading adjustments to the parking lot for the new building elevation and noted the addition of a clean-out manhole and modified sewer connection (from an in-surge to a Y-connection) per DPW request.

00:19:46 The sewer capacity study was described as in-progress. Information had been sent to DPW, and a meeting with Mark Noonan was pending to determine whether additional information or pipe repairs would be required. This study remained incomplete at the time of the meeting.

Landscaping and Lighting Updates

00:20:23 The landscaping plan was revised in response to DPW Director Gino Cresta’s directive that no trees be planted over the subsurface culvert that runs along the rear property line. Trees and evergreens were replaced with shrubs and grasses in those areas. An arborist survey confirmed that existing trees on the culvert could not be saved without risking future structural damage to the culvert.

A board member asked detailed questions 00:24:43 about the number and type of shade trees proposed. Lemieux enumerated eight shade trees total: one yellowwood, one elm, two honey locust, two maples, and two sycamores — all located away from the culvert.

00:21:24 The lighting design was modified to eliminate light spill onto abutting residential parcels. All fixtures would be shielded, with light directed only toward the roadway side (already lit by municipal lighting).

Two EV charging stations were added — one at a handicapped space and one at a standard space 00:22:13.

All abutting parcels in the rear and across Pine Street were surveyed to provide accurate setback measurements 00:22:32.

Architectural Updates

00:25:45 Architect Christopher Curran presented updates. The right-side porch stair was confirmed removed, with the entry now exclusively through the main entrance incorporating the accessibility ramp. Regarding the secondary egress-only door, Curran confirmed it would be alarm-triggered with hardware preventing it from being propped open, restricting it to emergency egress only.

00:27:20 Curran presented the shadow study, which modeled the building’s shade impact during the equinoxes, the summer solstice, and the winter solstice. The dark blue areas in the study showed where the building would cast shadows on neighboring structures at peak times.

00:28:15 An updated perspective rendering was shown comparing the current vacant site (with a porta-potty visible) to the proposed building as viewed from Pine Street. Curran emphasized that the gables and peaks of existing single-family homes across the street align with the second-floor line of the proposed building, and that the window scale and architectural detailing were designed to match the neighborhood context. He acknowledged the building is “a little bit bigger” than surrounding homes but argued “the scale is very similar.”

Construction Management and Fee Waivers

00:29:13 Varugood summarized additional commitments: a full construction management plan and pest control plan would be submitted as conditions of the building permit; the developer committed to sealed dumpsters, regular trash collection, and no overflow; and the monument sign design would be coordinated with the town prior to final approval.

00:29:41 Significantly, Varugood announced that the developer had withdrawn its request for permit and connection fee waivers, meaning all fees would be paid in full. This represented a concession from the developer’s prior position. Select Board Member Mary Ellen Fletcher later confirmed this point 00:36:17, specifically asking for clarification and being told the waiver requests were withdrawn.

Public Comment Period

00:31:15 Chair Heather opened the public comment period, requesting that comments focus on new questions or follow-ups to previously raised concerns.

Steve Gadman (11 Pine Street) 00:32:01 reiterated his concern that the proposed no-parking striping near the driveway entrance would displace cars from New Ocean Street apartments onto Pine Street, directly in front of residents’ homes. He urged the board to consider a single-entrance solution through the adjacent dispensary lot. Chair Heather acknowledged this was under active discussion, noting the developer had expressed willingness to explore options, and suggested tabling the no-parking question until the driveway configuration was resolved.

Gadman also asked about the culvert crossing under Pine Street 00:33:43. The civil engineer clarified that the culvert going south through the site would be relocated prior to construction, while the culvert running north and under the roadway would remain in place.

Alicia McCarthy (9 Pine Street) 00:34:34 asked where to find sewer documentation and expressed concern about culvert maintenance, noting the town had spent “countless hours cleaning them out every single day” over the past year. Chair Heather confirmed the sewer capacity study was still in progress with DPW and that all submitted documents were available on the town website through staff member Christa.

Mary Ellen Fletcher (Precinct 4, online) 00:36:17 requested clarification on the fee waiver withdrawal, which the Chair confirmed: all waivers would be withdrawn and all fees paid.

Developer’s Zoning Attorney 00:36:58 asked about the status and scope of the planned peer reviews. Chair Heather explained two peer reviews were contemplated: (1) parking and traffic, which would be held until the driveway configuration was resolved, and (2) the civil engineering plans, for which DPW Director Gino Cresta had recommended a reviewer.

Pine Street Resident (online) 00:42:17 suggested that if the dispensary lot entrance was infeasible, the driveway could be relocated to the end of Pine Street near New Ocean Street. The civil engineer raised safety concerns about that location, citing potential queuing issues around the Pine Street/New Ocean Street intersection and the loss of parking spaces. Chair Heather agreed the location was “a very dangerous spot for a driveway” given the road’s history, though committed to discussing it with Gino Cresta. A board member concurred that the single-entrance solution through the dispensary lot would be preferable.

Resident (noise question) 00:43:54 followed up on a prior request for information about decibel levels from rooftop mechanical equipment. A board member confirmed no relief from noise regulations was being sought, and that actual equipment specifications would be detailed in the building permit phase, which the board characterized as “good news.”

Peer Review Authorization Discussion and Vote

00:38:15 A board member raised whether the civil plans were sufficiently advanced for a peer review, given that the driveway configuration and sewer study remained unresolved. The civil engineer acknowledged these outstanding items but stated that if the driveway could not be relocated, the plans were essentially ready; if relocation proceeded, revised plans could be prepared within approximately two weeks.

00:39:26 The developer noted that driveway relocation would also implicate the town’s land development agreement and the dispensary’s existing lease of town-owned land, requiring coordination with the town.

00:40:29 A board member asked consultant Paul Havardy for his recommendation on timing. Havardy strongly recommended 00:41:16 getting peer review consultants on board as quickly as possible, even before plans were finalized: “I always recommend you get them on board as quickly as possible, even if you know you’re at a stage where you’re not quite ready for them to commence.” He reminded the board of the 180-day statutory deadline from the opening of the public hearing to complete the hearing process, noting “that goes very, very fast.”

00:44:50 The consultant asked whether the board would authorize the chair to proceed with engaging the peer reviewer, contingent on the proposed solution being reviewed by DPW.

00:46:02 Member Mike made a motion to designate Chair Heather as the board’s representative to work with DPW and other departments on the selection and engagement of the civil peer reviewer, with authority to commence the review if plans reached a sufficient stage. The motion was seconded.

00:46:42 A roll call vote was conducted. All present members voted in favor. Tony, the remote member, experienced continued muting difficulties but communicated his affirmative vote via text message to another board member. The Chair declared the vote unanimous.

Continuance to November 18

00:47:51 The Chair noted the next regular meeting would fall on the November holiday and confirmed the meeting had been rescheduled to November 18.

00:47:59 Member Mike moved to continue the public hearing to November 18. The motion was seconded and approved unanimously by voice vote. The hearing was adjourned.


Section 4: Executive Summary

Veterans Crossing 40B Project Advances with Revised Plans and Key Concessions

The Swampscott Zoning Board of Appeals held its second hearing session on the Chapter 40B Comprehensive Special Permit application for Veterans Crossing, a proposed affordable housing development on Pine Street being developed by Neighbourhood Housing (associated with B’nai B’rith Housing). The hearing, which opened September 16, is operating under the 180-day statutory deadline for the board to complete its review — a timeline that consultant Paul Havardy repeatedly emphasized moves quickly.

Significant Design Revisions Address Community Concerns

The developer presented a substantially revised plan set responding to feedback from both town staff and community members. The most consequential changes include:

  • Building elevation raised to 16 feet — two feet above the floodplain — providing climate resiliency while meeting building code.
  • One-way parking circulation that creates a loading area, increases setbacks from abutting properties, and enables a new landscaped buffer with fencing between the project and the dispensary lot.
  • Removal of a side staircase that would have allowed pedestrians to bypass the main entrance and exit directly onto the public sidewalk — a direct response to neighbor concerns about foot traffic management.
  • Elimination of light spill onto residential properties through shielded fixtures.
  • Addition of EV charging stations, including one ADA-accessible space.

Fee Waiver Withdrawal Represents Developer Concession

00:29:41 In a notable concession, the developer withdrew all requests for permit and connection fee waivers, committing to pay all fees in full. In the 40B context — where developers can request waivers of local fees as part of the comprehensive permit — this withdrawal removes a potential point of contention and represents a financial gesture of good faith toward the town.

Driveway Relocation Emerges as Central Unresolved Issue

The most significant unresolved question is whether the project’s driveway entrance can be moved off Pine Street. Neighbors strongly prefer access through the adjacent dispensary lot to avoid displacing on-street parking and routing traffic directly past their homes. The developer has expressed willingness to explore this option but noted it involves the town’s land development agreement and the dispensary’s lease of town land. Civil engineering and town coordination are underway, but no solution has been finalized.

Peer Review Engagement Authorized

00:46:02 The board unanimously authorized Chair Heather to engage a civil engineering peer reviewer in coordination with DPW, acting on consultant Havardy’s advice not to lose time before the next meeting. A separate traffic and parking peer review will be deferred until the driveway configuration is determined. The 180-day clock creates urgency for efficient scheduling.

Sewer and Culvert Studies Remain In Progress

The sewer capacity study is incomplete, with data submitted to DPW for review. The culvert running through the site — which has required extensive municipal maintenance — will be partially relocated, with trees removed per DPW Director Gino Cresta’s directive to prevent root damage. Resident Alicia McCarthy raised the important question of long-term culvert maintenance responsibility, which was not definitively answered.

Shadow Study and Scale Context Provided

The developer presented a shadow study and an updated perspective rendering intended to demonstrate that the building’s scale is compatible with the existing Pine Street neighborhood. The architect argued that the peaks of existing single-family homes align with the proposed building’s second-floor line, though acknowledged the building is larger than surrounding structures.

The hearing was continued to November 18, 2025.


Section 5: Analysis

A Productive but Incomplete Session

This second hearing on the Veterans Crossing 40B application was markedly more procedural and less contentious than a typical early-stage 40B hearing. The developer arrived with a detailed set of revisions responsive to prior feedback, and the board and abutters engaged in substantive but measured dialogue. The overall tone was collaborative rather than adversarial — a dynamic that reflects both the developer’s willingness to make concessions and the board’s awareness that the 40B process constrains its leverage.

The Driveway Question as Proxy for Deeper Tensions

The most revealing dynamic of the meeting centered on the driveway location. On the surface, this is a site design question. But it functions as a proxy for the fundamental tension in 40B projects: the impact of a multi-unit development on an established single-family neighborhood. Steve Gadman’s testimony 00:32:01 about displaced parking was concrete and specific — people from New Ocean Street apartments already “squeeze in places where they shouldn’t” — and represents the kind of lived-experience argument that carries weight in public hearings even when it doesn’t trigger formal regulatory standards.

The developer’s response — willingness to explore relocation through the dispensary lot — was tactically sound, acknowledging the concern without committing to a specific solution. The complication that this involves the town’s land development agreement and the dispensary’s lease adds a layer of institutional complexity that could slow resolution. The civil engineer’s candid warning 00:42:55 that an alternative New Ocean Street entrance would be “a very dangerous spot for a driveway” effectively narrowed the options to two: the current Pine Street configuration or the dispensary lot. This framing puts pressure on the town to facilitate the dispensary lot option if it wishes to address resident concerns.

The Fee Waiver Withdrawal: Strategic Concession

The withdrawal of fee waiver requests 00:29:41 is more significant than it might appear. In 40B proceedings, fee waivers are a common developer ask that can generate disproportionate public opposition — they are easily understood, easily resented, and politically visible. By removing this request, the developer eliminated a potential rallying point for opposition and signaled good faith. That Mary Ellen Fletcher, a Select Board member attending as a resident of Precinct 4, specifically sought clarification on this point 00:36:17 suggests its political salience was not lost on town officials.

Peer Review Timing Reveals the 40B Clock Pressure

The discussion about peer review timing [00:38:15–00:41:54] was the most procedurally important exchange of the evening. Consultant Paul Havardy’s intervention — urging the board to engage reviewers immediately even before plans were fully finalized — was informed by his experience with the 180-day statutory window. His reminder that “the time goes really quickly” 00:41:40 served as a gentle warning to a board that, understandably, wanted to wait for complete plans before committing to peer review expenses.

The board member who asked whether it made sense to wait for the driveway and sewer study to be resolved before engaging reviewers 00:38:15 was asking a reasonable question, but the answer from the consultant was clear: sequencing these steps linearly risks running out the clock. The unanimous vote to authorize the chair to proceed was a sensible response, preserving the board’s ability to conduct thorough review within the statutory timeframe.

Technical Presentations: Competent but Incomplete

The developer team delivered a polished presentation with specific, responsive revisions. The civil engineering changes — raised elevation, one-way circulation, increased setbacks, EV charging, shielded lighting — represent meaningful improvements. However, two significant studies remain incomplete: the sewer capacity analysis and the fire department review of the turning analysis. Alicia McCarthy’s question about long-term culvert maintenance 00:34:34 touched on a concern that extends beyond this project — the culvert has required intensive municipal attention — and the lack of a clear answer about future responsibility is a gap that will likely resurface.

The Shadow Study and Scale Argument

The architect’s presentation of the shadow study and perspective rendering [00:27:20–00:28:50] was designed to normalize the building’s scale relative to the neighborhood. The argument that existing roof peaks align with the second-floor line is a carefully chosen comparison point, but the candid acknowledgment that the building is “a little bit bigger” understates what is likely a substantial massing difference between a three-story multi-unit building and surrounding single-family homes. The board did not press this point at this session, though it may attract more scrutiny as the process continues.

Remote Participation Challenges

Tony’s persistent technical difficulties — inability to unmute, voting via text message — were handled pragmatically (the chair counted his text as a vote and noted the motion carried regardless). However, for a 40B hearing requiring a full board, ensuring reliable remote participation for future sessions will be important. The board’s lighthearted handling of the voicemail incident at the opening and Tony’s audio issues throughout reflected a relaxed informality that, while humanizing, underscored the hybrid meeting format’s limitations.

Looking Ahead

The November 18 continuation will be pivotal. By then, the board expects resolution — or at least clarity — on the driveway relocation feasibility, the sewer capacity study results, and progress on the civil peer review. The 180-day clock continues to run, and the number of outstanding items suggests the hearing will extend across several more sessions. The developer’s cooperative posture and willingness to make concessions has thus far maintained a constructive atmosphere, but the driveway question and the fundamental scale concerns of Pine Street residents remain live issues that will test that goodwill.